A ten-year transportation program approved by the Texas Transportation Commission on Aug. 27 projects $16.5 billion combined for TxDOT's two North Texas districts, Dallas and Fort Worth, out of a statewide plan of roughly $138 billion.
Within that regional figure, $491 million in the Dallas district and $200 million in the Fort Worth district is attached to Texas Clear Lanes, the state effort aimed at its most congested chokepoints. Denton County's Interstate 35W and Dallas County's Interstate 345 are listed for additional funding under the program, TxDOT's Dallas district says, with no start dates set.
None of those figures is a commitment. The program forecasts what could be funded rather than budgeting it, and a corridor listed in it has no guarantee of construction. TxDOT Dallas district public information officer Tony Hartzel has said funding levels can change and that the plan does not tie money to projects in a way that assures they will be built.
The Denton corridors
TxDOT's Dallas district says segments of Interstate 35W in Denton County received additional funding under the program, with no start date set.
I-35E through Denton from FM 2181 to US 380 appears on TxDOT's project list with no cost or schedule published; its listed public hearings were held in 2011 and 2005.